  • * Network Application is finished, stable and tested * All relevant data from BringAuto are gathered - stream information, camera calibration * BringAuto integrated the Network Application and confirms that it can run

    Overdue by 2 year(s)
    Due by April 28, 2023
    1/1 issues closed
  • * Feature freeze * Network application is finished and deployed in middleware * Client can use Network Application through middleware * Testing on locally deployed software on video recordings Successful test deployment means we can make first release - version 1.0.0 (and from then on we need to keep main branch clean and working, and also use strict version numbering)

    Overdue by 2 year(s)
    Due by March 24, 2023
    0/2 issues closed
  • * Core algorithm is wrapped in 5G-Era interface * Client application receives warning data

    Overdue by 2 year(s)
    Due by March 10, 2023
    8/8 issues closed
  • * Need to finish and test the core algorithm

    Overdue by 2 year(s)
    Due by March 3, 2023
    11/11 issues closed