that's a doubt and then a suggestion. (I will send .mpp file by email)
When i update percentage of project tasks and then change their calendar, in timephaseds the values are based on the new calendar, consequently, changing what has already been done. Sample below:

Screenshot 2023-08-14 154418
Screenshot 2023-08-14 154633

is it possible to keep the values already been done ?