Date calculations based on business calendars.
To get business, simply:
$ gem install businessGet started with business by creating an instance of the calendar class, passing in a hash that specifies with days of the week are considered working days, and which days are holidays.
calendar = Business::Calendar.new(
working_days: %w( mon tue wed thu fri ),
holidays: ["01/01/2014", "03/01/2014"], # array items are either parseable date strings, or real Date objects
working_dates: ["08/01/2014"]
)working_dates parameter makes the calendar to consider a weekend day as a working day.
A few calendar configs are bundled with the gem (see lib/business/data for
details). Load them by calling the load class method on Calendar. The
load_cached variant of this method caches the calendars by name after loading
them, to avoid reading and parsing the config file multiple times.
calendar = Business::Calendar.load("weekdays")
calendar = Business::Calendar.load_cached("weekdays")Config files are YAML files that look such simple as:
working_days:
- monday
- tuesday
- wednesday
- thursday
- friday
holidays:
- January 1st, 2017
- March 8th, 2017
- May 1st, 2017
working_dates:
- January 8st, 2017If working_days is missing, then common default is used (mon-fri).
If holidays is missing, "no holidays" assumed.
If working_dates is missing, then no changes in working_days will happen.
Elements of holidays and working_dates may be
eiter strings that Date.parse() can understand,
or YYYY-MM-DD (which is considered as a Date by Ruby YAML itself).
working_dates:
- 2017-01-08 # Same as January 8th, 2017You may find a few sample config files in lib/business/data/ directory.
To check whether a given date is a business day (falls on one of the specified
working days, and is not a holiday), use the business_day? method on
Calendar.
calendar.business_day?(Date.parse("Monday, 9 June 2014"))
# => true
calendar.business_day?(Date.parse("Sunday, 8 June 2014"))
# => falseTo use a calendar you've written yourself, you need to add the directory it's stored in as an additional calendar load path:
Business::Calendar.additional_load_paths = ['path/to/your/calendar/directory']You can then load the calendar as normal.
The add_business_days and subtract_business_days are used to perform
business day arithemtic on dates.
date = Date.parse("Thursday, 12 June 2014")
calendar.add_business_days(date, 4).strftime("%A, %d %B %Y")
# => "Wednesday, 18 June 2014"
calendar.subtract_business_days(date, 4).strftime("%A, %d %B %Y")
# => "Friday, 06 June 2014"The roll_forward and roll_backward methods snap a date to a nearby business
day. If provided with a business day, they will return that date. Otherwise,
they will advance (forward for roll_forward and backward for roll_backward)
until a business day is found.
date = Date.parse("Saturday, 14 June 2014")
calendar.roll_forward(date).strftime("%A, %d %B %Y")
# => "Monday, 16 June 2014"
calendar.roll_backward(date).strftime("%A, %d %B %Y")
# => "Friday, 13 June 2014"To count the number of business days between two dates, pass the dates to
business_days_between. This method counts from start of the first date to
start of the second date. So, assuming no holidays, there would be two business
days between a Monday and a Wednesday.
date = Date.parse("Saturday, 14 June 2014")
calendar.business_days_between(date, date + 7)
# => 5Another gem, business_time, also exists for this purpose. We previously used business_time, but encountered several issues that prompted us to start business.
Firstly, business_time works by monkey-patching Date, Time, and FixNum.
While this enables syntax like Time.now + 1.business_day, it means that all
configuration has to be global. GoCardless handles payments across several
geographies, so being able to work with multiple working-day calendars is
essential for us. Business provides a simple Calendar class, that is
initialized with a configuration that specifies which days of the week are
considered to be working days, and which dates are holidays.
Secondly, business_time supports calculations on times as well as dates. For our purposes, date-based calculations are sufficient. Supporting time-based calculations as well makes the code significantly more complex. We chose to avoid this extra complexity by sticking solely to date-based mathematics.